May,
2002
Land access issues simmer in New Mexico
Federal officials are still weighing
development options 41/2 years after Harvey E.
Yates Co. (HEYCO, Roswell, New Mexico) made the
first commercial gas discovery in the Orogrande basin. The Bennett Ranch Unit
1 Y well testing gas at the rate of 4.4 MMcfd
from about 4,500 ft. The discovery well is on federal land
in an area referred to as Otero Mesa, 40 miles east-northeast of El
Paso, but gas deposits are believed to range over large areas in the
Orogrande basin. After HEYCO's discovery, other companies and
individuals nominated almost 400 sq miles in New Mexico for federal
leasing. No more leases have been granted. Orogrande potential is likened
to the 19 tfc of gas equivalent that has been produced from the pre-Leonardian
formations in Eddy, Lea, Chavez, and Roosevelt counties, an area of
similar size and geology in the New Mexico portion of the Permian
Basin.
BLM prepared a resource management Plan
Amendment covering Sierra and Otero counties published in late
2000. In it the BLM placed no surface occupancy restrictions on
large areas, including most tracts adjacent to the discovery
well. At best this would sour project economics by requiring
more expensive directional drilling. HEYCO objected to that plan as too
restrictive to even allow for drilling. Recently the BLM
proposed that no more than 5% of the surface of any lease be
disturbed. Non development interests, mainly the New Mexico
Wilderness Alliance have argued that drilling and roads will spoil the
view, ruin potential habitat for the endangered, Apomado falcon and
damage the Chihuahua desert. HEYCO argued that the country needs
the gas and that the company is entitled to make a profit. On Feb.
28th, the BLM Resources Advisory Council recommended that HEYCO
and non-development interests to negotiate an acceptable
alternative.
|
|
|
|
- Summarized form "Land Access issues simmer in
California, Utah, and New Mexico" Oil and Gas Journal. pp.
50-51 March 18, 2002
|
|
Traffic Jams for Seismic Permits
In late February, an Interior Department appeals officer halted oil
exploration near Arches National Park in Utah. He said that the
project could cause irreparable damage to the area. Officials at
the Bureau of Land Management said that they had considered the
concerns of those who questioned the project before any activity
began. The BLM now plans to give additional information to the
Interior's board of Land Appeals, justifying the project. Stuart
Wright (a speaker at RMAG's annual symposium in Denver)
commented that any area which falls within a national park, national
monument, wilderness area, wilderness study area or other less common
areas of specific consideration, is automatically subject to
regulatory review. In all it takes about 90-120 days to obtain a
federal permit for seismic studies on BLM land, and an additional
15-40 days for actual acquisition of data from a 20 square mile survey.
In general it takes about 137 days (4-5 months) to obtain federal
permits. And that is an optimistic estimate. Another
problem encountered with the project is that companies can only shoot
seismic when the tundra is not frozen (August to September).
Other factors that may play in on the time restraints are Raptor
nesting dates, sage grouse strutting time restrictions, Elk calving
time restrictions, and hunting seasons. Finally when towns,
railroads, interstate highways, topographic barriers, and private land
owners are considered, the process for acquiring seismic data on
federal lands becomes increasingly more complicated.
|
|